East Broadway Construction Update 1/22

Dear East Broadway / East Somerville Community Member,

Happy New Year!


You are receiving this notification as part of the City of Somerville’s community notification process. You have signed up to receive alerts and information pertaining to ongoing construction on East Broadway, and as part of this process you will receive several emails per month with status updates and schedules for the project through its completion. Throughout the project, updates, schedules and other relevant information can be found at www.somervillema.gov/alerts/city-construction-updates.
For the period between Jan. 21 and Feb. 8, the construction schedule is as follows (please note that all dates are subject to change due to inclement weather):
  • Weeks of Jan. 21, Jan. 27, and Feb. 3:
    • Sewer pipe installation. Autumn St. and Rush St. areas. For this work, both Autumn St. and  Rush St. will be closed to through traffic during work hours on these dates. Abutters will be allowed to access the street, and police details will assist with all detours during work hours.
  • Tue., Jan. 21:
    • Pipe bursting at Autumn St. If your property is to be affected, you will be notified by work crews in advance.
  • Tue., Jan. 21 and Wed., Jan. 22:
    • Sewer work at Cross St.
  • Tue., Jan. 21 through Thurs., Jan. 23:
    • Sewer work at Autumn St.
    • Relocation of traffic signals at Cross St.
  • Wed., Jan. 22:
    • Patching trenches. Cross St. to Autumn St.
  • Fri., Jan. 24:
    • Rodent abatement project-wide.
    • Patching trenches. Cross St. to Autumn St.
  • Week of Jan. 27:
    • Sewer work. Cross St. East to Minnesota Ave.
  • Wed., Jan. 29:
    • Patching trenches. Cross St. to Autumn St.
  • Fri., Jan,. 31:
    • Patching trenches. Cross St. to Autumn St.
  • Week of Feb. 3:
    • Sewer work. Minnesota Ave.
  • Wed., Feb. 5:
    • Patching trenches. Cross St. to Autumn St.
  • Fri., Feb. 7:
    • Patching trenches. Cross St. to Autumn St.
 The full three week look ahead is attached here, and available on the City’s construction updates website. If you have questions, please do not hesitate to contact one of the project staff:
  • The City of Somerville’s Constituent Service Center: 311 (617-666-3311 from outside the City), 311Updates@somervillema.gov
  • City of Somerville, Deputy Director of Communications, Jackie Rossetti: 617-625-6600 ext 2614
  • Massachusetts Department of Transportation Project Manager, George Kavalaris: (781) 853-8055
 Thank you!