Dear East Broadway / East Somerville Community Member,
You are receiving this notification as part of the City of Somerville’s community notification process. You have signed up to receive alerts and information pertaining to ongoing construction on East Broadway, and as part of this process you will receive several emails per month with status updates and schedules for the project through its completion. Throughout the project, updates, schedules and other relevant information can be found at www.somervillema.gov/alerts/city-construction-updates.
For the period between Nov. 4 and Nov. 16, the construction schedule is as follows:
You are receiving this notification as part of the City of Somerville’s community notification process. You have signed up to receive alerts and information pertaining to ongoing construction on East Broadway, and as part of this process you will receive several emails per month with status updates and schedules for the project through its completion. Throughout the project, updates, schedules and other relevant information can be found at www.somervillema.gov/alerts/city-construction-updates.
For the period between Nov. 4 and Nov. 16, the construction schedule is as follows:
- Thursday, Oct. 31 through Tuesday, Nov. 5 (except weekends): Backfilling sidewalks to proper elevation prior to laying concrete. Garfield Ave. to Cross Street.
- Friday, Nov. 1:
- Pouring concrete. MacArthur Street to Garfield Ave. This work will impact properties until concrete has set. Work crews can assist you with access to your property.
- Rodent abatement project-wide.
- Week of Nov. 4: Water main work. Cross St. East to Illinois Ave. This work involves minor roadway excavation at the gutter/curb, but water service will not be interrupted.
- Monday, Nov. 4:
- Pouring concrete. MacArthur Street to Garfield Ave., and Garfield Ave. to Cross Street. This work will impact properties until concrete has set. Work crews can assist you with access to your property.
- Preparation work for amenities. Garfield Ave. to Cross Street. This work will include the installation of tree grates and frames on sidewalks.
- Monday, Nov. 4 through Wednesday, Nov. 6: Excavation of island at MacArthur Street to Garfield Ave. Vehicle traffic will be one lane during work hours.
- Wednesday, Nov. 6 through Friday, Nov. 8: Curb installation on the traffic island at MacArthur Street to Garfield Ave. Vehicle traffic will be one lane during work hours.
- Friday, Nov. 8: Utility work, traffic island at MacArthur Street to Garfield Ave. Vehicle traffic will be one lane during work hours.
- Tuesday, Nov. 12 through Thursday, Nov. 14: Utility work, traffic island at MacArthur Street to Garfield Ave. Vehicle traffic will be one lane during work hours.
- Tuesday, Nov. 12 through Friday, Nov. 15: Sewer lining. There are little to no impacts from this work.
- Friday, Nov. 15: Rodent abatement project-wide.
- The City of Somerville’s Constituent Service Center: 311 (617-666-3311 from outside the City), 311Updates@somervillema.gov
- City of Somerville, Deputy Director of Communications, Jackie Rossetti: 617-625-6600 ext 2614
- Massachusetts Department of Transportation Project Manager, George Kavalaris: (781) 853-8055
This
e-mail has been sent to you by the CITY OF SOMERVILLE. To maximize
their communication with you, you may be receiving this e-mail in
addition to a phone call with the same message. If you wish to
discontinue this service, please inform the CITY OF SOMERVILLE either IN
PERSON, by US MAIL, or by TELEPHONE at 617-628-7669 or REPLY TO THIS
EMAIL.
No comments:
Post a Comment